Engineering, procurement, construction and commissioning of Compressor Station No. 1 at section 110 km of Kazakhstan-China main gas pipeline
Activity Area: Oil and gas industry
Client: Asian Gas Pipeline LLP
Country: Kazakhstan
Date of completion: 30.11.2017
Construction period: 47 months
Project description
Compressor station No. 1, consisting of 3 gas turbine compressors with 30 MW capacity.