280, Baizakov Street, Almaty

Construction of Expansion of Gas Treatment Plant at Akshabulak field

Activity Area: Oil and gas industry

Client: Kazgermunai LLP JV

Country: Kazakhstan

Date of completion: 29.08.2012

Construction period: 68 months

Construction of Expansion of Gas Treatment Plant at Akshabulak field

1

Construction of Expansion of Gas Treatment Plant at Akshabulak field

2

Construction of Expansion of Gas Treatment Plant at Akshabulak field

3

Construction of Expansion of Gas Treatment Plant at Akshabulak field

4

Construction of Expansion of Gas Treatment Plant at Akshabulak field

5

Construction of Expansion of Gas Treatment Plant at Akshabulak field

6

Construction of Expansion of Gas Treatment Plant at Akshabulak field

7

Construction of Expansion of Gas Treatment Plant at Akshabulak field

8

Construction of Expansion of Gas Treatment Plant at Akshabulak field

9

Construction of Expansion of Gas Treatment Plant at Akshabulak field

10

KazStroy
Service

KazStroy
Service

KazStroy
Service

KazStroy
Service

KazStroy
Service

KazStroy
Service

KazStroy
Service

KazStroy
Service

KazStroy
Service

KazStroy
Service

1

2

3

4

5

6

7

8

9

10

1 / 10
Back to the list

Contact us

We will promptly reply to your questions on design, procurement, industrial construction, etc.